Current Transformer and Monitoring Relay: Ratio, Burden and Input Checks

A current transformer and current monitoring relay must be matched by input type, ratio, secondary rating, burden, frequency and the exact relay measurement range. Do not connect an ordinary current-output CT to a relay simply because both devices display amperes. Confirm that the relay manufacturer permits that interface, document how primary current is converted into a setting, and provide an approved maintenance arrangement. A conventional CT secondary must not be opened while primary current may flow. This guide addresses interface selection and commissioning evidence; it does not authorize live secondary-circuit work or establish compatibility for an unspecified product version.

Identify the relay input before selecting a sensor

A current monitoring product can measure through a direct series input, an integral aperture, an external current transformer, or another sensor interface. These arrangements require different wiring and interpretation. A product’s control supply terminals are not automatically its measurement input. Start with the exact wiring diagram and identify the measured conductor, the sensing terminals and the separate supply circuit where applicable.

Asiaon’s ASC18 current monitoring relay lists multiple AC and DC measurement ranges. That range table is useful for narrowing an inquiry, but it does not by itself establish that every version accepts every external CT. Request written confirmation of the intended sensor interface, input burden and overload limits for the precise ordering code before designing the circuit.

An AC current transformer is also different from a DC current sensor. A conventional transformer does not provide a steady DC measurement by applying the usual AC ratio relationship. If the monitored circuit carries DC, specify a suitable sensing technology and a compatible relay input. Do not choose the DC suffix of a monitoring relay and assume that a conventional AC CT completes the measurement chain.

Treat ratio and setting scale as separate records

A CT ratio relates rated primary and secondary currents under its specified operating conditions. A relay connected to the secondary may display secondary amperes, primary amperes after configured scaling, or a percentage of a selected range. The setting instructions decide which interpretation is correct. Keep the ratio record separate from the relay scale so that a replacement technician can reconstruct the decision.

For an idealized calculation, let the nominal primary current be 100 A and nominal secondary current 5 A. The nominal ratio is 100 / 5 = 20. A primary current of 60 A then corresponds to 60 / 20 = 3 A secondary. Conversely, a secondary setting of 4 A corresponds nominally to 4 × 20 = 80 A primary. These values are arithmetic examples, not an approved ASC18 installation or recommended alarm setting.

Real selection must account for accuracy, operating range, waveform, frequency, temperature and the CT’s specified burden conditions. Ratio arithmetic cannot establish measurement quality near the bottom of a range or during a severe transient. The equipment designer must decide whether the chain is suitable for process indication, an alarm or a defined protective function, and obtain evidence appropriate to that purpose.

Account for the complete secondary burden

The Schneider Electric’s CT safety guidance explains why a conventional CT must remain connected to a suitable burden or approved shorting arrangement when primary current may flow. For a purchasing review, request the sensor’s burden capability and the relay’s input burden, then include the wiring and other connected equipment in the calculation. Do not compare only the relay’s nominal current with the CT nameplate.

ASV18 voltage monitoring relay
ASV18 voltage monitoring relay. Original Asiaon product photograph; consult the exact ordered version documentation.

For a purely resistive arithmetic example at a specified operating point, apparent burden can be estimated as S = I²R, with S in VA, I in amperes and R in ohms. If the complete secondary loop resistance is 0.10 ohm at 5 A, the result is 5² × 0.10 = 2.5 VA. This simplified calculation excludes reactive effects and does not replace the CT manufacturer’s accuracy and burden requirements.

Include the full outgoing and return conductor length when calculating loop resistance. Record the conductor material, size and relevant temperature assumption. If several devices share a secondary circuit, document the approved connection arrangement and each contribution. An extra meter added during a later panel modification can change the burden even though the monitoring relay itself remains untouched.

Review item Evidence to record Acceptance action
Input type Direct, current-output or voltage-output sensor Require exact input compatibility
Ratio Primary and secondary rated values Document primary-to-secondary conversion
Burden Relay, wiring and connected equipment Check complete loop against CT conditions
Scale Secondary, primary or percentage setting Avoid duplicated ratio conversion
Maintenance Isolation and approved shorting arrangement Never open a live current-output CT burden
Function Threshold, delay and recovery Verify complete signal-chain response

Keep current-output CT safety explicit

For a conventional current-output CT, removing the connected burden while primary current flows can create a dangerous secondary voltage. Do not use a normal terminal-disconnection habit from a voltage circuit as a CT maintenance procedure. The safe arrangement must be designed in advance and handled by qualified personnel using approved isolation, shorting and test equipment appropriate to the installation.

A shorting facility is not permission to experiment with a live circuit. Define who may operate it, the approved sequence, identification and verification requirements. Where possible, plan work with the primary circuit deenergized and verified safe. The electrical work practices in 29 CFR 1910.333 provide a reference for isolation and verification in applicable workplaces; local requirements and site procedures also govern the task.

Not every device called a CT has the same output arrangement. Some sensors incorporate a burden and provide a voltage output, while other measurement technologies provide electronic signals. Identify the actual construction and instructions before applying maintenance rules. Do not short an unspecified voltage-output sensor merely because a conventional current-output CT requires a safe burden path.

Separate current monitoring from voltage monitoring

A current signal describes the monitored current at its sensing point. It does not independently establish that the supply voltage is healthy, that phase sequence is correct or that a motor is mechanically safe. A current monitoring relay can be one input to a machine’s diagnostic logic, but the system designer must define what the signal proves and which faults require other measurements.

ASP18 three-phase voltage relay
ASP18 three-phase voltage relay. Original Asiaon product photograph; consult the exact ordered version documentation.

Asiaon’s ASV18 voltage monitoring relay belongs to a different measurement function. Its photograph in this guide illustrates the need to distinguish nearby DIN rail monitoring products by their documented function, not by enclosure appearance. It is not a CT receiver recommendation. Likewise, the ASP18 three-phase voltage relay should be evaluated for its stated voltage-monitoring options rather than used as evidence about current-input compatibility.

Where the application uses both voltage and current information, create a signal list with the sensing point, healthy state, fault state and controller response for each channel. This helps prevent a technician from substituting a physically similar monitoring device that cannot provide the required measurement. Keep supply requirements and output contact duties in that same record.

Commission the measurement chain in stages

Before energization, review the approved drawings, part numbers, terminal identification and sensor orientation. Verify that the chosen test method will not create an unsafe CT secondary condition. Check that the relay scale and ratio information agree with the calculation sheet. Record any software scaling in the controller as well, because duplicated scaling can make an apparently plausible display wrong by a large factor.

Use an approved calibrated source or commissioning method to establish known input conditions within the equipment’s permitted limits. Record the reference value, relay indication or state, applicable delay and resulting controller response. A test of a relay alone establishes less than a test of the complete installed chain. Identify exactly which boundary the test covered and which elements remain outside it.

Include recovery and loss-of-supply behavior in the functional plan. The relay may return to a healthy output while the machine should still require a deliberate restart. Validate that distinction in the controller logic. A current threshold check cannot establish restart safety or certify a protective function that the complete system has not been designed and assessed to provide.

Prepare a replacement and inquiry checklist

Send the supplier the monitored current type, normal and transient range, frequency, sensor model, ratio, secondary rating and proposed burden calculation. Add the exact monitoring relay code, supply voltage, output duty and expected alarm behavior. Ask for the approved input wiring and confirmation of whether the proposed sensor is supported. A clear interface question is more useful than asking whether a relay can handle a motor’s full current.

For a replacement, preserve the accepted ratio, settings, terminal labels and circuit identification before changing parts. Compare the replacement’s input characteristics instead of copying only the dial position. A different measurement range can make the same dial position represent a different primary current. Update the circuit record and spare-parts list after the replacement has passed the agreed checks.

Keep calibration and functional records together, but distinguish them. Calibration concerns the measurement relationship under stated conditions; functional verification concerns the configured response of the installed system. An alarm can operate at the expected threshold while the displayed primary current is scaled incorrectly. Both checks matter when operators rely on the display to understand a developing process fault.

Frequently asked questions

Can any five-ampere relay input be connected to a five-ampere CT?

No. Nominal current is only one compatibility condition. Confirm input type, burden, frequency, overload capability, range and the manufacturer’s approved interface. Also evaluate the CT’s operating conditions and the complete secondary circuit. A matching number on two labels does not settle those requirements.

Does changing the CT ratio require changing the relay setting?

It requires reviewing the whole scaling chain. If the relay works in secondary amperes, the same setting may represent a different primary threshold. If scaling is configured in the relay or controller, update and verify it using a documented calculation and an approved functional test.

Can a monitoring relay be unplugged for a quick CT check?

Do not disconnect a conventional current-output CT burden while primary current may flow. Use the approved maintenance and isolation arrangement established for that circuit. Qualified personnel must identify the sensor type and safe test boundary before removing equipment or changing secondary connections.

Video: measurement and circuit background

The Engineering Mindset explains transformer principles. This is background for understanding magnetic coupling, not permission to disconnect a current transformer or a CT maintenance procedure.

Watch Transformers Explained – How transformers work on YouTube

Related relay planning guides

For control component fundamentals, start with our general-purpose relay selection guide. Continue with Current Monitoring Relay Settings: Threshold, Delay and Reset, and Voltage Monitoring Relay Settings: Limits, Delay and Recovery.