A timer relay power failure reset requirement must state what happens to the elapsed time, output and next start command when supply disappears and returns. A timer may restart a full interval, wait for a new trigger, retain timing information, or provide a specifically designed delayed release. The correct behavior comes from the exact function diagram and order code, not the words “on delay” or “off delay” alone. Before approving a replacement, define the required recovery sequence and test it with the actual control circuit, including the state of any trigger that remains active during the interruption.
Begin with a recovery requirement, not a timer label
Write a short process statement: after an interruption, which equipment may operate, what must remain stopped, and what action authorizes a new cycle? This statement should come from the machine’s control design and risk assessment. The timer implements part of that sequence; selecting a familiar front-panel range does not establish the whole restart behavior.
Keep the timer supply, trigger input and controlled load separate on the drawing. They may lose power at different times. A controller may remain energized while a timer supply drops, or the timer may remain energized while a trigger disappears. These are different events and must not share an ambiguous “power fail” label in the test sheet.
The AST18-X multifunction time relay is a starting product reference. Confirm the selected version’s function chart, supply option, terminal drawing and reset conditions with the applicable documentation. This guide does not assign AST18-X a memory function, interruption tolerance or guaranteed restart interval that has not been verified for the ordered version.
Distinguish supply interruption from trigger removal
A powered timer can observe an input changing while its internal circuit continues operating. Removing its supply can prevent that same circuit from continuing, unless the device has a documented mechanism or stored energy for the required function. A trigger-controlled off-delay arrangement therefore must not be assumed to behave identically after complete supply loss.
The technical overview in EC&M’s time-delay relay article distinguishes common timing functions and specifically separates true off-delay behavior from a powered trigger-controlled arrangement. Use this as general background. It is not an AST18 specification, and the overview’s example circuits are not complete designs for a particular machine.
Ask the supplier to identify the initiating event and reset event directly on the selected chart. If a statement says “reset when power is removed,” ask for any specified minimum interruption duration and recovery conditions. A brief voltage dip that does not complete an internal reset is not necessarily equivalent to a deliberate long shutdown.

The AST18-P photograph illustrates a single-function timer family. Similar-looking timer fronts can conceal different function choices, ranges or input arrangements. Retain photographs for identification, but make the written acceptance decision against the full code and documentation. Never transfer terminal assumptions from one model to another because the width or adjustment knobs appear similar.
Define elapsed time, output state and authorization separately
Three questions make a useful recovery specification. First, is elapsed timing discarded, retained or recalculated? Second, what happens to the output during the interruption and immediately after recovery? Third, what permits a new cycle? An answer to only the first question leaves the machine behavior incomplete.
For example, a process may require a fresh full delay after every interruption, yet also require an operator start command before the delay begins. A timer that resets its elapsed time but starts automatically when power returns may meet the timing requirement and still violate the process requirement. The surrounding control circuit must implement the needed authorization independently where appropriate.
Conversely, a process that allows automatic recovery may need proof that a held trigger starts exactly one cycle, rather than repeatedly initiating it. Describe both the expected first event after restoration and the rearming condition for the next event. This prevents disagreement between the person selecting the timer and the person programming or wiring the rest of the system.
| Review item | Evidence to record | Acceptance action |
|---|---|---|
| Elapsed time | Restart, retain or wait requirement | Compare with selected function chart |
| Output on loss | Required contact and load condition | Observe output and downstream feedback |
| Held trigger | Signal remains active through restoration | Check first cycle and rearming |
| Short interruption | Published reset and supply conditions | Test agreed durations without inventing a minimum |
| Recovery permission | Automatic or deliberate new start | Verify complete machine control sequence |
| Replacement | Code, supply, terminals and chart revision | Approve after interruption tests |
This is a qualitative acceptance worksheet, not a list of universal timer behaviors. Use it with the selected function chart and the machine’s documented recovery requirements. Where the required behavior cannot be established, leave that selection open rather than treating an untested assumption as a specification.
Build a complete interruption test matrix
Test an interruption before timing starts, while timing is active, after the output has transferred, and during the return to the initial state. Where the application permits interrupted operation, include the period just before the planned timeout. A test performed only at startup can overlook a restart that occurs after an almost completed cycle.
For each point, vary the trigger state in a controlled way: inactive before recovery, held active through recovery, and changed after recovery. Record the actual voltage at the timer and any separate trigger supply. The test record should show the command, timer output and relevant load feedback on a common time base, so a delayed output is not confused with a slow downstream device.
Use interruption durations justified by the product’s published conditions and the application’s supply events. Do not improvise a universal minimum reset time. If the manufacturer’s information does not cover a required disturbance, request clarification or conduct an agreed qualification programme. A bench observation can document a tested condition without proving performance at every voltage, temperature or interruption duration.
Include brownouts and partially powered interfaces
An interrupted supply is not always a clean change from rated voltage to zero. A decaying supply, repeated short dips or a shared control supply affected by a large load may produce a different sequence. Measure the relevant supply conditions before deciding that the timer has ignored a reset. Check connections and supply capacity as part of the investigation.
A separately powered input can also remain active when the timer’s own supply is absent. The permitted electrical relationship between these terminals must come from the device documentation. Do not assume an input can be energized with its supply disconnected, or add a jumper to force recovery. Review interface ratings, reference connections and any restrictions on independently powered signals.
If supply quality is the problem, correct that issue before changing the timing setting. Extending a delay may conceal a recovery symptom but cannot establish that the internal circuit resets reliably. Keep the original settings and traces so that any repair can be evaluated against the same event rather than a changed operating sequence.
Check restart safety in the whole machine
A standard timing relay does not, by itself, establish a safety-rated restart prevention function. The required safety architecture, diagnostics and validation belong to the machine design. A timer’s output returning to its initial state is only one observable condition; it does not prove that stored energy is removed or that another path cannot energize the actuator.
For US workplace servicing, 29 CFR 1910.147 addresses control of hazardous energy and prevention of unexpected energization or startup during maintenance. Treat this as a servicing reference within its scope, not as a complete machine design standard. The local rules and approved isolation procedure govern the work.
Testing should be planned by qualified personnel with the controlled equipment in an appropriate test condition. Keep the service isolation procedure separate from the functional restart test. A stop command or a timer set to a long interval is not a substitute for the required means of energy isolation. Record who authorizes restoration before a test sequence begins.

The AST18-2T product image supplies a distinct single-function timer reference. A dedicated function may simplify selection when it matches the required sequence, but fewer controls do not remove the need to verify reset and recovery. Compare its selected version with the requirement rather than assuming that any single-function timer is easier to interchange.
Distinguish time accuracy from reset performance
A timer can meet a steady-state timing requirement and still be unsuitable for the required restart sequence. Check the published timing accuracy, repeatability, reset conditions, recovery behavior and supply operating conditions as separate items. Make sure the time range and adjustment method permit the desired setting without depending on an uncertain dial position.
Use the actual triggering event as the timing reference. In a supply-started function, a measurement taken from a controller command may include supply switching delay before the timer begins. In a signal-started function, measuring from power restoration can include the wait for a trigger. State which interval was measured so future service technicians can reproduce the result.
When the process requires a total delay, include downstream relay operation, contactor movement, controller scanning and any communications involved. A timer’s own interval is only part of the sequence. Do not promise a machine response based on a timer setting alone; validate the complete path under the conditions the process requires.
Prepare a replacement approval package
Collect the old full model code, settings, wiring diagram, function chart and reason for replacement. Add a required-state table for supply loss and restoration, including held-trigger behavior. Record whether the process permits an automatic restart and which separate controls provide any required inhibition. Ask for clarification when the old installation has no documented recovery requirement.
For the proposed part, request matching evidence for the supply, terminals, timing function, output duty and recovery behavior. Retain the applicable document revision with the purchase record. Perform the agreed interruption tests on the first installation before extending the replacement to other machines. A matching mounting width and voltage label are useful screening details, but they do not constitute functional approval.
Frequently asked questions
Does a timer always start from zero after power returns?
No universal assumption is safe. The exact function and version determine whether timing restarts, waits for a trigger or retains information. Verify the chart and published reset conditions, then test the required interruption and trigger combinations in the actual circuit.
Is trigger removal the same as switching off the timer supply?
No. A powered timer may continue timing after its trigger changes, while complete supply loss can alter or stop its internal operation. A specifically designed true off-delay function is a separate case. Confirm the ordered device’s behavior rather than inferring it from the general function name.
Can a longer delay prevent an unexpected restart?
A longer delay changes when an output operates; it does not establish authorization to restart. Define the required recovery state and implement the approved control measures. Validate the machine’s entire restart sequence, including signals that remain active while power is absent.
Video: measurement and circuit background
Khan Academy explains stored charge and RC natural response. This provides background for why power removal and internal energy decay are different events; it does not establish an AST18 reset time or energy storage design.
Watch RC natural response intuition (1 of 3) on YouTube
Related relay planning guides
For control component fundamentals, start with our general-purpose relay selection guide. Continue with on-delay and off-delay function selection, and repeat-cycle timing and first-state checks.