Repeat Cycle Timer Relay: ON/OFF Times, First State and Reset

A repeat cycle timer relay alternates an output between an active interval and an inactive interval while its enabling conditions remain satisfied. To specify it correctly, define which interval happens first, how the two durations are adjusted, and what occurs after a stop, reset or power interruption. “Repeat cycle” alone does not establish those details. For intermittent ventilation, signaling or another approved repetitive process, a clear sequence description is more useful than a timer family name. This guide shows how to turn the required sequence into settings, calculate the resulting cycle and verify an actual timer without assuming undocumented behavior.

Describe one complete cycle before choosing hardware

Write the process in observable states. For example: after an approved start command, energize a control output for an interval, return it to the inactive state for another interval, then repeat until the enable condition ends. Specify whether the first interval is active or inactive. Also identify what “active” means in the equipment: an energized timer output relay is not necessarily the same thing as a running load.

Normally open and normally closed contacts produce different load behavior. A timing diagram should therefore name both the output relay state and the chosen contact path. Otherwise two people can agree on an “ON-first” timer and still wire opposite load sequences. The final circuit drawing must resolve that ambiguity before commissioning.

The Sathyabama PLC and Automation course material includes an on-off cycle example to explain recurring timing logic. It is useful background for interpreting state transitions. A standalone timer’s own timing chart remains the authority for its terminals, controls and reset behavior.

Distinguish a repeating cycle from a single delay

An on-delay function waits before changing an output after its initiating condition. An off-delay function delays a specified return transition. Neither name alone means that the device repeats indefinitely. A repeat cycle function performs successive active and inactive intervals under its documented enabling conditions.

Likewise, two independently adjustable delays do not automatically make a cyclic timer. The AST18-2T product is described as a double ON-delay unit. Its photograph below illustrates why similar housings and multiple settings are insufficient selection evidence. Compare the function description and timing chart rather than assuming the controls have the same meaning across models.

AST18-2T double ON-delay timer relay
AST18-2T double ON-delay timer relay. Original Asiaon product photograph; use the exact ordered version documentation.

For a process requiring different active and inactive durations, the AST18-S asymmetric cycle timer is a directly relevant product reference. Its public page identifies selectable starting ON and starting OFF behavior. Confirm the exact ordered version, output arrangement and current instructions before applying any setting procedure.

Choose the initial state deliberately

An active-first sequence begins with the output’s active interval when timing starts. An inactive-first sequence waits through the inactive interval before producing the first active interval. The difference matters when the equipment should remain idle while a system stabilizes or when the first operation must happen promptly after a permitted start.

Separate that initial sequence from what happens after an ordinary pause. A pause may suspend timing, clear timing or inhibit the output, depending on the product and function. Do not use the words pause, stop and reset interchangeably. Write the expected transition for each actual control input in the sequence specification.

Test the starting behavior at the selected contact terminals, rather than relying only on a front-panel LED. An indicator can help troubleshoot, but the controlled circuit is what determines whether the intended process begins in the correct state.

Establish what each setting controls

Some timers expose separate active and inactive durations. Others use a period together with a ratio or a related adjustment method. A multifunction model may give the same control a different meaning in another mode. Read the supplied setting instructions and map every control to a variable in the required sequence.

Do not assume that the label T1 always means active time. It may represent the first interval, which could be inactive in an OFF-first sequence. Similarly, a percentage control needs a defined reference: active time divided by total cycle time is different from active time divided by inactive time. Record the manufacturer’s definition alongside the desired settings.

The AST18-S page provides time-setting and ratio-setting references. Obtain and read those diagrams at a usable size. If the wording or drawing leaves an ambiguity, confirm the interpretation with the supplier and prove it on a controlled bench test before connecting the process load.

Review item Evidence to record Acceptance action
First interval Active-first or inactive-first Observe the selected contact path
Active duration Required time and setting definition Measure output active time
Inactive duration Required time and setting definition Measure output inactive time
Adjustment method Independent times or period/ratio Use the exact model instructions
Interruption Stop, reset and supply-loss behavior Test both intervals
Switching duty Load type and cycles per operating hour Review applicable contact endurance

Basis: application review checklist and the linked product documentation. No additional product ratings or unverified setting values are implied.

Calculate period, duty and switching frequency

For a sequence with active duration Ton and inactive duration Toff, the total period is T = Ton + Toff. The active duty fraction is D = Ton / T. Multiply D by 100 to express the result as a percentage. Both durations must use the same units and must represent the actual output sequence being discussed.

For an illustrative process with 12 seconds active and 48 seconds inactive, T is 60 seconds and the active duty is 20%. The sequence repeats 60 times per hour while enabled. These are example process requirements, not default AST18-S settings. A ratio-controlled timer still needs its documented conversion from these requirements to its front-panel values.

At one complete cycle per minute, eight hours of continuous enable creates 480 cycles. Count contact transitions according to the manufacturer’s endurance terminology when assessing wear. A complete active/inactive cycle contains two state changes, but data sheets may define their operation counts differently. Check the applicable definition rather than comparing unlike numbers.

Duty fraction does not by itself establish motor suitability, valve cooling or electrical endurance. The load may have startup limits, minimum resting time or a permitted starts-per-hour value. Confirm these separately with the equipment documentation and the approved process design.

Keep timing control separate from load approval

A timer’s output contact rating must suit the circuit it switches. An output used to command a contactor has a different duty from one switching a heater or motor directly. Nominal current alone does not describe inrush, interruption or the effect of repeated switching. The UNLV relay guide explains why motor starting demand and contact lifetime deserve separate attention.

Choose the switching arrangement using the actual load data and the timer’s applicable rating. If an intermediate device is required, include its coil demand and suppression in the control review. Do not infer that a repetitive timing function authorizes unlimited direct switching of a load merely because its running current looks small.

AST18-X multifunction timer relay
AST18-X multifunction timer relay. Original Asiaon product photograph; use the exact ordered version documentation.

Define power-loss and restart behavior

A short supply interruption can affect timing differently from a deliberate stop command. The timer may reset, resume or follow another documented sequence. State explicitly whether the process is allowed to restart automatically after power returns, and whether it must restart from the first interval.

The timer’s available behavior must fit the equipment’s restart policy. Where an unexpected start could create a hazard, the required interlocks and safety functions must come from the machine assessment. A standard cyclic timer is not a substitute for a validated safety control system.

Include interruptions during both active and inactive intervals in the acceptance test. Record the duration and nature of each interruption. A successful cold power-up does not demonstrate what happens after a brief dip or after a start signal is removed while the timer’s supply remains present.

Verify settings using a controlled sequence test

Before connecting the process load, qualified personnel should verify the exact order code, supply, selected function and output terminal map. Use an appropriate test circuit and measure the actual transitions. Label the observed signal so it is clear whether the measurement represents the timer contact or the downstream load.

Measure several complete cycles, including the first interval. Compare the results with the process tolerance and the timer’s stated accuracy under the relevant conditions. A setting resolution, setting deviation and repeat accuracy are different characteristics; none should be substituted for the complete application’s acceptable timing error.

Then test stop, reset, loss of supply and restoration. Check whether changing a setting during operation takes effect immediately or on a later cycle, if that behavior is documented and relevant. Otherwise establish a procedure to isolate or stop the equipment before changing settings.

For electrical work, use the applicable local procedures. The U.S. electrical work requirements reproduced by Cornell LII provide a reference for deenergization and verification. Switching the timer output off does not isolate every energy source in the equipment.

Prepare a purchase and commissioning record

An effective inquiry states active and inactive durations, initial state, supply type and voltage, output contact requirements, trigger method and restart policy. Include expected daily operating hours, load characteristics and mounting conditions. Request the exact timing chart and setting instructions for the proposed part.

The commissioning record should preserve the ordered code, function choice, units, settings and measured results. Photograph controls where useful, but retain written values so an unreadable dial position does not become the only service record. Make approved setting changes traceable to the process requirement they satisfy.

Is an asymmetric timer different from an equal-interval flasher?

An asymmetric cycle allows different active and inactive durations according to the selected product’s setting method. Confirm both the available function and how its controls translate into time.

Does OFF-first mean that the load is definitely disconnected first?

It describes a timing state, which must be mapped to the chosen contacts and circuit. A normally closed load path can produce behavior different from a normally open path.

Can I use the duty percentage to predict contact life?

No. Contact life also depends on the switched load, inrush, interruption conditions, operation count and the manufacturer’s test basis. Evaluate those conditions together with the timing requirement.

Video: background for the control and measurement checks

RealPars explains the relay output principle and the distinction between control and load circuits. Use this foundation when mapping the timing states to contacts; the video does not teach AST18-S settings.